How many times have you been completely confused at how that ’small’ project turned into such a big one costing double and taking three times the length you estimated? Many of you will say estimating time for web projects accurately is an oxymoron, but by applying a few effective techniques it’s possible to dramatically increase the accuracy of most web project estimates.
1. Why Underestimating Is So Common
There are several reasons, which are freely admitted amongst freelancers and web agencies, as to why web projects are so commonly underestimated - they include:

However, there are also some secret reasons why web projects are commonly underestimated:
Despite being true, rarely do we admit these reasons to others or even ourselves! The fact is, when working as a web professional, as a one man band or as part of a small busy web team, the secret reasons are an everyday reality that shouldn’t be hidden away.
By first identifying and admitting why underestimating is so common, can you then set about implementing changes to your estimating process that will reduce the barriers each reason creates and increase your accuracy.
Technologies Not Used Before
There are three approaches you can take when confronted with a brief that requires a technology you have minimal experience with:
Try to negotiate with the client a mini-project where you are paid to conduct a research and functional planning stage before committing to the whole project. This way you can research the unfamiliar technology and deliver a functional specification to the client.

Best case scenarioYou give the client confidence, have a much clearer understanding of the work required, re-estimate and are hired for the rest of the project.
Worst caseYou have completed foundation learning of a technology you previously didn’t know that you can sell to new clients, you generate revenue and the client has a comprehensive specification they can use in their tender process.
Added bonusYou, and the client, get to find out how you work together, giving both the opportunity to part company before being locked into a lengthy project.
If you’re not able to convince the client to pay for this initial functional planning stage, and can’t find a suitable expert in the technology, but want the work and have confidence in your ability and passion to learn what needs to be learnt, then the best advice is to do some initial research in your own time and just take your best guess!
Estimating Takes Too Long
Thorough web project estimating takes time, but it tends to inherit all the same rules that apply to coding, the more thorough you are, the more accurate you’ll be.
Is it possible you will spend time working out the features required only to learn you haven’t won the work? Will you have given the client a free and detailed breakdown of their project for free? Absolutely, but this is the just nature of sales, some you win, some you lose - don’t get disheartened, try to get feedback from the client on why you didn’t win and use the advice given to refine your next estimation.
Estimate Is Needed Tomorrow
If a client is demanding an estimate tomorrow after briefing you on the project today you should immediately try to assess if the project is right for you by:
If the results of these quick steps are favorable, be positive and go for it! There will be another chance to decline if you later find out the project is not right for you, and then you may utter the words “Into the garbage chute, flyboy!”

Cash Flow Dilemma
Cash flow is the life blood of any freelancer or small web agency, without they don’t survive.
Occasionally a situation may arise where work will be taken on with the knowledge it may not be profitable. As gut wrenching as this can be, and despite all the comments you will hear how you should never do this, the reality is the bills and wages have to be paid!
When a freelancer or business owner is presented with the choice of committing to a project for a price they know is low, but by taking on the project means they live to fight another month, or risking not taking on the work on in the hope more profitable leads appear - empathise with and respect them.
It is a tough and gutsy decision that only they can make but rest assured they have their bills or your wages at the forefront of their mind when they make it and estimating low for a project isn’t always as naive a decision as it may appear to those not on the frontline.
Estimating Is Not Fun
Ok, so it’s not as sexy as adding that beautiful grunge effect to your design, and it’s not as exciting as tweaking that jQuery plugin to work just the way you want, but estimating time for a web project more accurately is almost certainly more important than both when it comes to sustaining a freelance or small web agency business.
However, while few will disagree as to its importance, many will continually find it difficult to muster up the passion and diligently estimate time for a web project, but why!? Here are more secret reasons:
Web agencies often have the edge here because they will have dedicated salespeople or project managers who are used to the rigors of estimating, but freelancers will generally be more inclined to find the whole process rather boring and just want to get on with the fun stuff.
While we can all no doubt empathise with this, the harsh truth is that, when running a small business or operating as a one man band, one or two badly estimated projects in quick succession can ultimately lead to the demise of both!
So what other techniques can be used to further increase the accuracy of your estimates?
2. Consistent Project Phases And Tasks
As previously mentioned, when being asked to provide an estimate for a project, it is invariably not something anyone has allocated time to do. As a result of this, estimates are often put together quickly and if compared to past estimates it’s not uncommon to see the same project phase or task classified in many different ways, and for similar sized projects the estimates for each to be completely different.

If you win the work you may think “so what?”, and to some extent you would be right, however, the first step in creating more accurate estimates on a long-term basis is to always break down the project phases and tasks in a consistent manner. Web projects can generally be broken down into the following phases:
By always beginning to compile estimates using a consistent high-level breakdown means you can have a re-usable template eventually and track the time spent on each.
But don’t stop there! Consistently breaking each phase down further will not only increase the accuracy of the estimate, but again, also result in valuable data over time.
3. Getting Granular

Now the project estimate is broken down into high-level phases, it’s time to get more granular and break each phase into tasks. This is where the estimate begins to become more tailored to the specific project, but also includes common tasks that you can add to your estimating template and use again and again. For example:
The page templates and features specific to the client’s project can be listed at this stage, alongside the tasks required in all web projects.
Once you get into the habit of compiling estimates in this way you will find yourself envisaging the phase and tasks lists during the pre-sales initial communication with the client and this invariably:
So, you now have a pretty solid phase and task list for the project and all that’s left is to estimate hours for each and send it off to the client right? Maybe, but wait, what exactly does the News feature consist of? Is your interpretation of a News feature the same as the client’s?
Now is the time to investigate and define it, as opposed to after the contracts have been signed.
Getting More Granular
While it’s tempting to estimate hours for the News feature and submit to the client, if possible, try to nail down exactly what the client wants from this feature at the estimating stage, after all, if you look around, you’ll be able to quickly find different variations of the same feature that have a huge differences in terms of size, features and complexity, and thus cost.
Using the News feature as an example, talk to the client and determine what it needs to do so that you can again minimise the chances of missing something in your estimate that could, when added to the other ’small’ missed tasks, amount to a serious budget overrun situation.
You may find out the News feature requirements are:
Excellent, you have now defined the News feature and can confidentially estimate the time you think it will take to implement. But hidden in even the most basic and common of features lay more ’small’ things that if not captured, considered and quoted on, can add to the likelihood of overrun.
For example, the client has specified they need to be able to upload images to news items, but do they need any of the following:
Any of the above News features could add a few hours to the overall project and thus need to be ideally catered for in your estimates - a few missed ‘couple of hours’ tasks and suddenly the project is two days over budget.
Getting granular and mentally trying to build the solution means you are able to identify and address these issues early on, making sure to cater for them in your final estimate.
“A Web Project Manager knows how to design and develop most of the project on his own, even if with poorer results compared to his team. This allows him to estimate projects with good approximation and to understand his team’s problems and difficulties”
Introduction to Web Project Management, Antonio Volpon
Advantages Of Getting Granular, For You And The Client
By getting granular with project phases and tasks for estimates you are also able to tweak them very quickly if you discover the estimate you have submitted is above the client’s maximum budget.
For example, how often have you been told by a client they want to go with you but your quote is ‘just a little too high’ and ‘if you could reduce it by five hours we can business’? Usually this means you have to do one of two things; drop the hours you estimated for the News feature and hope you can explain later down the line how the budget does not allow for image uploads and thumbnail generation etc., or remove the News feature altogether.
But, if you have a granular estimate for the News feature, you can confidentially, and at this crucial expectation setting stage, simply remove a couple of sub-features of News and the News image upload functionality in order to align with the client’s budget.
When communicating this to the client they will clearly see what you are proposing to drop and why and they will still get the News feature they need, but perhaps with a few less nice to haves. Using this approach is usually well received by clients as they have full and transparency on the reasoning behind the changes to your proposal.
This kind of transparency during the sales process will invariably give the client confidence in you because it demonstrates to them you:
Best of all, if you are successful with your estimate and you are hired you already have the foundations of:
So what now? Well, now you have won the work, it’s time to start collecting the data that will enable you to create even more accurate estimates in the future.
4. Consistent Time Tracking And Analysis
Before starting the work, you should first replicate all of the phases and tasks, along with their time estimates, into your time tracking tool of choice. Once this is done, you can then begin work and make sure to be disciplined and track everything you do and log it under the right category.

Of course many of you will do this by default as it allows you to:
But the real value of keeping a consistent set of high-level phases, from estimate through to time tracking, is that after a few projects you can begin toanalyse the data and start to identify averages and trends that you can use to refine your next web project estimate.
Analyse Estimated vs. Actual Time
This is where the real magic happens! By breaking down and tracking your time for multiple projects into consistent phases and tasks, you will have valid comparable data to analyse, for example, after five projects, once you average out the numbers, you may well discover the following:
The more projects completed that use a consistent estimating and time tracking structure, the more real your averages will become.

With this valuable information you can then set about increasing the accuracy of your next estimate by being able to, assuming you can get a budget range from the client:
It even allows you to accommodate the client that ‘needs an estimate tomorrow’ when you don’t have time to break it down in detail.
Conclusion
Estimating time for a web project accurately is something many attempt everyday but few manage to succeed at. There is no one formula that will satisfy every situation and the chances of estimating what a project will cost exactly are almost zero.
But it is possible to drastically increase the accuracy of your web project estimates by:
“The Devil is in the detail: When people say that the devil is in the detail, they mean that small things in plans and schemes that are often overlooked can cause serious problems later on.”
Further Resources
Here are further articles and related resources that may help you to increase the accuracy of your web project estimates:
Related posts
You may be interested in the following related posts:
About the author
Sam Barnes is a Web Project Manager at Rawnet. Although a little short for a Stormtrooper, he can be found posting articles at thesambarnes.com, a blog dedicated to the subject of Web Project Management.
© Sam Barnes for Smashing Magazine, 2009. |